Valmet has been selected in a new public procurement process as the tenderer for completing the biomass boiler, flue gas cleaning and flue gas condensing system works for Vilnius Combined Heat and Power Plant (Vilnius CHP) in Lithuania. Vilnius CHP is working on a modern heat generation capacity expansion project in the Vilnius central heating system.

The new public procurement process was needed since the original contractor was unable to complete the works.

The order is included in Valmet’s orders received of the second quarter 2022. The total maximum value of the order is around EUR 30 million.

Mantas Burokas, CEO at Vilnius CHP, said:

We have now concluded with Valmet one of the most important and critical contracts for Vilnius CHP’s biomass project.

“We still need to initiate the operation of the technical equipment of the biomass boiler plant, which will allow us to generate electricity and heat”.

Niina Ollikka, Director of Boiler Rebuilds and Conversions, Energy business unit, Valmet, said:

We are happy to contribute to an important project for Vilnius city’s residents.

“We plan to launch the power plant to the testing phase in the first quarter of 2023”.

Information about Valmet’s delivery

Valmet will perform a technical assessment of biomass boilers, complete the biomass boiler, flue gas cleaning and flue gas condensing system installation works, carry out commissioning works (cold and hot tests), train the power plant’s personnel and prepare the instructions for using the biomass unit.

Information about Vilnius CHP

After the Vilnius CHP project is completed, the power plant’s total electricity capacity will amount to 90 MW (70 MW biomass based), and the heating capacity will amount to roughly 230 MW (170 MW biomass based).

Since 2020, the power plant has been generating energy using municipal waste. After the biomass project is complete, energy will also be generated using biomass.

The waste-to-energy unit incinerates about 160,000 tonnes of municipal waste and turn it into energy. The biomass unit will burn about 500,000 tonnes of biomass per year.

READ the latest news shaping the biofuels market at Biofuels Central

Valmet to complete biomass boiler, flue gas cleaning and flue gas condensing system works at Vilnius Combined Heat and Power Plant in Lithuania, May 11, 2022

biofuels central news

Get our LinkedIn updates!

Join our weekly newsletter

Follow us

Don't be shy, get in touch. We love meeting interesting people and making new friends.